FE Industrial and Systems Manufacturing, Service, and Other Production Systems Practice Problems

The current FE Industrial and Systems specification assigns 9-14 of the 110 exam questions to Manufacturing, Service, and Other Production Systems. Form A contains 10 original problems in this area. The sample below is published in full, with the same worked-solution format used throughout the book.

Free sample problem

A line completes 420 units during 7.0 operating hours. Average throughput is most nearly:

  1. (A)60 units/h
  2. (B)75 units/h
  3. (C)90 units/h
  4. (D)120 units/h
Show worked solution

Answer: (A)

Throughput is 420/7=60 units per hour.

The process, inventory, or flow relation determines system performance.

Substitution and unit reduction give the reported value.

FE Reference Handbook — Production Systems: Throughput

Why the other choices appear

  • (B)This introduces an extra factor of 1.25 that is not present in the governing relation.
  • (C)This value is 50% above the verified result; no stated conversion creates that change.
  • (D)The units are retained, but an unsupported 2 multiplier changes the requested magnitude.

The complete FE Industrial and Systems practice exam contains 10 problems in this area and 110 problems overall, with an answer key, full solutions, and a score sheet by knowledge area.

Retaking this exam? The FE exam retake guide turns the NCEES diagnostic report into an area-by-area plan.