FE Industrial and Systems Engineering Economics Practice Problems

The current FE Industrial and Systems specification assigns 9-14 of the 110 exam questions to Engineering Economics. Form A contains 10 original problems in this area. The sample below is published in full, with the same worked-solution format used throughout the book.

Free sample problem

A project receives 25,000 USD at each year-end for four years. At 6%, present worth is most nearly:

  1. (A)21657 USD
  2. (B)43314 USD
  3. (C)64971 USD
  4. (D)86628 USD
Show worked solution

Answer: (D)

The four-payment present worth is about 86,628 USD.

The cash flows and costs are placed on the requested economic basis.

Substitution and unit reduction give the reported value.

FE Reference Handbook — Engineering Economics: Present Worth

Why the other choices appear

  • (A)This introduces an extra factor of 0.25 that is not present in the governing relation.
  • (B)This value is 50% below the verified result; no stated conversion creates that change.
  • (C)The units are retained, but an unsupported 0.75 multiplier changes the requested magnitude.