FE Environmental Solid and Hazardous Waste Practice Problems

The current FE Environmental specification assigns 7-11 of the 110 exam questions to Solid and Hazardous Waste. Form A contains 7 original problems in this area. The sample below is published in full, with the same worked-solution format used throughout the book.

Free sample problem

A transfer station ships municipal solid waste to a regional landfill in transfer trailers with a 20 ton payload. The round-trip haul distance is 120 mi and the hauling contract pays USD 2.85 per mile of travel. Transfer station processing costs USD 7.40 per ton. The combined processing and haul cost is most nearly:

  1. (A)USD 15.95 per ton
  2. (B)USD 17.47 per ton
  3. (C)USD 24.50 per ton
  4. (D)USD 41.60 per ton
Show worked solution

Answer: (C)

Haul charges of 17.10 USD/ton over the round trip plus the 7.40 USD/ton processing fee total 24.50 USD/ton.

Haul payment is earned on every mile travelled, so the stated round-trip distance already covers the loaded and the empty leg.

Payload sets the accounting basis, because one trailer carries the whole load charge.

Transfer station processing is already quoted on a mass basis and adds without conversion.

FE Reference Handbook — Engineering Economics: Cost Estimation, Unit Cost Basis

Why the other choices appear

  • (A)Halves the given distance to a one-way 60 mi haul: 60 x 2.85/20 + 7.40 = 15.95 USD/ton.
  • (B)Treats the 7.40 USD/ton processing fee as a per-load charge: (342 + 7.40)/20 = 17.47 USD/ton.
  • (D)Doubles an already round-trip mileage to account for the return leg twice: 2(342)/20 + 7.40 = 41.60 USD/ton.

The complete FE Environmental practice exam contains 7 problems in this area and 110 problems overall, with an answer key, full solutions, and a score sheet by knowledge area.